Although we didn't go up there today, I called Scott and asked if they had finished the forms for the walls today. He said that they said that they would be done in time for the concrete truck to start pouring the walls for the basement this afternoon.
He said that they should be able to pour the walls today. Tomorrow they should be able to remove the forms from around the walls.
Saturday a plumber is coming to put in the pipes in the basement floor so that they can be ready to pour the basement floors early next week. Still looking like subfloors early next week and hopefully logs by later that week.